Naksapass — the municipal building permit — is where a design becomes a legal right to build. Done properly it is a predictable process; done casually it becomes months of resubmission. Here is how we prepare a file.

What goes in the file

Exact requirements vary by municipality, but a complete Kathmandu-Valley application generally carries:

The sequence, in plain terms

  1. File registration at the municipality — the file is checked for completeness, not correctness, at this stage.
  2. Technical review — a municipal engineer checks setbacks, FAR, height, light plane and code compliance against the drawings.
  3. Site verification (sarjamin) — the plot, access and boundary claims are verified on the ground with neighbours notified.
  4. 15-day public notice — a statutory window for objections.
  5. Permit up to plinth level — you may build to DPC. A municipal inspection at plinth then releases the superstructure permission for the rest of the building.
  6. Completion certificate (निर्माण सम्पन्न) after final inspection — needed later for utility connections, bank loans and resale.

Where files stall — and how we prevent it

A clean first submission is the whole game. Municipal reviewers approve files that answer questions before they are asked.


Treta prepares and follows naksapass files as a standard part of design — one team, one responsibility. Ask us about your plot.