◆ Guide — engineer-reviewed
Naksapass, prepared properly: documents & process
नक्सापास तयारी: कागजात र प्रक्रिया
Naksapass — the municipal building permit — is where a design becomes a legal right to build. Done properly it is a predictable process; done casually it becomes months of resubmission. Here is how we prepare a file.
What goes in the file
Exact requirements vary by municipality, but a complete Kathmandu-Valley application generally carries:
- Lalpurja (ownership certificate) and a recent trace map from the Survey Office
- Citizenship certificate of the owner
- Land-tax (malpot) clearance receipt for the current year
- Architectural drawings — site plan, floor plans, elevations, sections at the municipal scale
- Structural drawings and design report — required for framed structures under the current building code (NBC)
- Signatures of the licensed designer and, where required, the structural engineer
- Neighbour's consent (sandhiyar) where openings or walls sit on a shared boundary
The sequence, in plain terms
- File registration at the municipality — the file is checked for completeness, not correctness, at this stage.
- Technical review — a municipal engineer checks setbacks, FAR, height, light plane and code compliance against the drawings.
- Site verification (sarjamin) — the plot, access and boundary claims are verified on the ground with neighbours notified.
- 15-day public notice — a statutory window for objections.
- Permit up to plinth level — you may build to DPC. A municipal inspection at plinth then releases the superstructure permission for the rest of the building.
- Completion certificate (निर्माण सम्पन्न) after final inspection — needed later for utility connections, bank loans and resale.
Where files stall — and how we prevent it
- Setback mismatch between the drawing and the actual road width → we measure the road ourselves before drawing.
- Trace map older than the site reality (subdivided plots, widened roads) → we reconcile survey data first.
- Structural set missing or generic → our structural drawings are produced for the specific plot and soil, not copied.
- Owner unavailable for sarjamin → we schedule the site visit and stand with you on the day.
A clean first submission is the whole game. Municipal reviewers approve files that answer questions before they are asked.
Treta prepares and follows naksapass files as a standard part of design — one team, one responsibility. Ask us about your plot.